NGT (National Green Tribunal) allowed the Delhi Metro Rail Corporation (DMRC) to construct a bridge on the Yamuna flood plains under Phase-IV of the project. The order has been passed NGT Chairperson Adarsh Kumar Goel. The bench comprises of Justice S P Wangdi also stated, ” to ensure further environmental safeguards for river Yamuna and its flood plains on account of such activities in future, besides individual evaluation of such projects on the environmental yardstick, cumulative impact assessment (CIA) is required to be carried out while others members of bench also stated that “The Principal Committee may also consider setting up of artificial wetlands, bio-diversity parks and other necessary mitigation measures, including phytoremediation at the mouth of drains leading to the river, at the cost of project proponents. The study may be got conducted by Principal Committee, by apportioning the cost amongst project proponents based on the quantum of development and their environmental footprints.
The Principal Committee had recommended that all the construction activities should be carried out by DMRC with minimum effect on the flood plains. may also consider setting up of artificial wetlands, bio-diversity parks and other necessary mitigation measures, including phytoremediation at the mouth of drains leading to the river, at the cost of project proponents. The study may be got conducted by Principal Committee, by apportioning the cost amongst project proponents based on quantum of development and their environmental footprints.
“Restoration of the flood plain that may be impacted adversely or otherwise by the construction of bridge alignment in the Yamuna flood plain/ pillars. The muck/debris generated should be disposed off scientifically and no dumping shall be allowed on the flood plains. Compensation of the trees to be cut during construction/ operational phase of the project to be carried out by DMRC without fail,” the committee said.
The Supreme Court has passed the order which said that phase-IV of Delhi Metro project be implemented without delay.